T1 - Research and application of hard rock deep-hole advance blasting in comprehensive roadway excavation
AU - Wang, Hai Bo
AU - Xu, Xuan
AU - Zong, Qi
AU - Xu, Shao Ming
AU - Xu, Ying
N1 - Publisher Copyright:
© 2017, Editorial Office of Journal of China Coal Society. All right reserved.
PY - 2017/4/1
Y1 - 2017/4/1
N2 - Deep hole advance blasting technology is adopted for hard rock roadway excavated by comprehensive tunneling machine. It can increase the fracture and damage scope of rock mass, and make the comprehensive tunneling machine cutting easier. Take Taoyuan Coal Mine of Huaibei Mining Group as an example, the theoretical analysis and numerical simulation on the blasting crack and damage range of original rock stress were conducted, on the basis of this, the parameters of large diameter deep hole advance blasting was designed and tested. The research results show that the range of Von Mises stress more than 177 MPa was 0.424 m around blasting hole, the hole diameter was 75 mm, the charge diameter was 63 mm, and a fracture zone was formatted. Its damage range was from 0.424 m to 2.3 m. After blasting, comprehensive machine excavation speed increased by 40% to 50% and cutter consumption was reduced by 52.4%. Blasting vibration measurement and analysis show that blasting vibration energy was focused on the frequency range from 50 Hz to 160 Hz, and there was no damage to the roadway surrounding rock and supporting structure.
AB - Deep hole advance blasting technology is adopted for hard rock roadway excavated by comprehensive tunneling machine. It can increase the fracture and damage scope of rock mass, and make the comprehensive tunneling machine cutting easier. Take Taoyuan Coal Mine of Huaibei Mining Group as an example, the theoretical analysis and numerical simulation on the blasting crack and damage range of original rock stress were conducted, on the basis of this, the parameters of large diameter deep hole advance blasting was designed and tested. The research results show that the range of Von Mises stress more than 177 MPa was 0.424 m around blasting hole, the hole diameter was 75 mm, the charge diameter was 63 mm, and a fracture zone was formatted. Its damage range was from 0.424 m to 2.3 m. After blasting, comprehensive machine excavation speed increased by 40% to 50% and cutter consumption was reduced by 52.4%. Blasting vibration measurement and analysis show that blasting vibration energy was focused on the frequency range from 50 Hz to 160 Hz, and there was no damage to the roadway surrounding rock and supporting structure.
KW - Comprehensive roadway
KW - Damage range
KW - Deep hole advance blasting
KW - Hard rock
UR - http://www.scopus.com/inward/record.url?scp=85027129790&partnerID=8YFLogxK
U2 - 10.13225/j.cnki.jccs.2016.0799
DO - 10.13225/j.cnki.jccs.2016.0799
M3 - Article
AN - SCOPUS:85027129790
SN - 0253-9993
VL - 42
SP - 908
EP - 915
JO - Meitan Xuebao/Journal of the China Coal Society
JF - Meitan Xuebao/Journal of the China Coal Society
IS - 4