A heuristic algorithm for solving resource constrained project scheduling problem with transfer time under resource bundle

Junqi Cai, Zhihong Peng

科研成果: 书/报告/会议事项章节会议稿件同行评审

1 引用 (Scopus)

摘要

In this paper we investigate an extension of Resource Constrained Projected Scheduling Problem (RCPSP): the Resource Constrained Project Scheduling Problem with Transfer Time under Resource Bundle. For this complex problem, the use of a parallel scheduling scheme is proposed. Such scheme has been successfully applied to the RCPSP. Introducing transfer time and resource bundle into RCPSP causes two problems, one is the possibility of resources significantly exceed the need of a task, the other is cooperation among unfamiliar members from different team may increase the makespan of the project. In order to deal with the problem, two new concepts are developed: task-related resource weight and collaboration coefficient. Some discussion of such concepts is given of and use them for new heuristic framework we proposed. A computational test is performed and the results show that the new heuristic is very effective in finding better solutions within a very short time.

源语言英语
主期刊名Proceedings of the 38th Chinese Control Conference, CCC 2019
编辑Minyue Fu, Jian Sun
出版商IEEE Computer Society
2155-2160
页数6
ISBN(电子版)9789881563972
DOI
出版状态已出版 - 7月 2019
活动38th Chinese Control Conference, CCC 2019 - Guangzhou, 中国
期限: 27 7月 201930 7月 2019

出版系列

姓名Chinese Control Conference, CCC
2019-July
ISSN(印刷版)1934-1768
ISSN(电子版)2161-2927

会议

会议38th Chinese Control Conference, CCC 2019
国家/地区中国
Guangzhou
时期27/07/1930/07/19

指纹

探究 'A heuristic algorithm for solving resource constrained project scheduling problem with transfer time under resource bundle' 的科研主题。它们共同构成独一无二的指纹。

引用此