T1 - A column generation based distributed scheduling algorithm for multi-mode resource constrained project scheduling problem
AU - Changchun, Liu
AU - Xi, Xiang
AU - Canrong, Zhang
AU - Qiang, Wang
AU - Li, Zheng
N1 - Publisher Copyright:
© 2018 Elsevier Ltd
PY - 2018/11
Y1 - 2018/11
N2 - This study develops a column generation-based distributed scheduling algorithm for multi-mode resource constrained project scheduling problem. The proposed distributed algorithm shares less information among independent decision makers compared with the traditional integrated approach. In this problem, many independent processors, which can produce different types of products, coordinate with a resource manager (or third-party logistic), who provides different types of vehicles to deliver products to the customers. The problem is decomposed into two parts: production planning for individual processors and vehicle scheduling for the resource manager. A total of 1200 instances are randomly generated to verify the effectiveness of the proposed distributed algorithm. Results of computational experiments verify that the proposed distributed algorithm has good solution quality and calculation efficiency compared with the integrated approach, i.e., CPLEX, hybrid Benders Decomposition, and Lagrangian Relaxation. Lastly, a general framework for the distributed algorithm is proposed to solve a generalized problem.
AB - This study develops a column generation-based distributed scheduling algorithm for multi-mode resource constrained project scheduling problem. The proposed distributed algorithm shares less information among independent decision makers compared with the traditional integrated approach. In this problem, many independent processors, which can produce different types of products, coordinate with a resource manager (or third-party logistic), who provides different types of vehicles to deliver products to the customers. The problem is decomposed into two parts: production planning for individual processors and vehicle scheduling for the resource manager. A total of 1200 instances are randomly generated to verify the effectiveness of the proposed distributed algorithm. Results of computational experiments verify that the proposed distributed algorithm has good solution quality and calculation efficiency compared with the integrated approach, i.e., CPLEX, hybrid Benders Decomposition, and Lagrangian Relaxation. Lastly, a general framework for the distributed algorithm is proposed to solve a generalized problem.
KW - Column generation
KW - Distributed scheduling
KW - Information-sharing
KW - Multi-mode resource constrained project scheduling problem
UR - http://www.scopus.com/inward/record.url?scp=85052751730&partnerID=8YFLogxK
U2 - 10.1016/j.cie.2018.08.036
DO - 10.1016/j.cie.2018.08.036
M3 - Article
AN - SCOPUS:85052751730
SN - 0360-8352
VL - 125
SP - 258
EP - 278
JO - Computers and Industrial Engineering
JF - Computers and Industrial Engineering
ER -